Will the lifts run? The research behind the Lift Outlook
A working paper on forecasting ski-lift operations from weather, and the honest rules that keep a probability from pretending to be a report.

Tämä artikkeli ei ole vielä saatavilla suomeksi, näytämme englanninkielisen alkuperäisen.
A skier booking a week in the Alps in October is not asking what the weather will be. They are asking whether the mountain will be open: whether most of the lifts will turn, whether the sectors that link the villages will be connected, whether the run home will still be skiable at four in the afternoon. Every forecasting product answers a different question, snowfall, temperature, snow depth, and leaves the skier to infer operations from weather. That inference is the hard part, and it is mostly wrong at the edges of the season and on windy days.
Since 3 September every resort page on Skinow carries a Lift Outlook: the chance that most lifts run, per day, from tomorrow to the end of the season. Behind it is a research paper we are writing in the open, with the evaluation protocol frozen before the first winter label exists. This post summarises it. The draft itself is embedded below and will change as the season fills in the results.
The question, stated honestly
Lift operations are a decision, not a state of the atmosphere. An operator closes an exposed chairlift at a gust threshold particular to that installation, opens the season on a date set months earlier, and runs a reduced network on a Tuesday in January for reasons of demand rather than snow. So the paper treats operations as the target and weather as the input, and it never lets the two blur. On the site, the outlook is a probability, worded as likely, chance or typically, dated, and labelled a model estimate. The verified open or closed statement next to it comes only from an operator report. The two are kept in separate tables and separate sentences, on purpose, and a test suite pins the boundary.

Where the labels come from
Nobody publishes a history of lift operations. Real-time status is everywhere, on dozens of vendor systems, but it evaporates the next morning. We log it: an append-only ledger reads operator and aggregator sources at a polite cadence, and a nightly job turns each resort-day into a label with one central rule: the absence of a report is unknown, never closed. An explicit closed report is a real zero. The day's label is the day's maximum share of lifts running, and when two sources disagree both rows stay, because the disagreement is a result.
For the past, the only record turned out to be the web archives. Per-resort snow-report pages were captured a few times each winter back to 2012 by the Wayback Machine, and Common Crawl's monthly crawls, on a schedule of their own, fill the winters the Wayback Machine barely touched. Each capture carries the lift count of that day. We map those pages to our catalogue, fetch every winter capture once, and pair the resort-day with the weather of that day. After the complete pass over both archives (12 September 2026), 1,285 of our 1,659 resorts have such a page on one aggregator and 634 on another, and the harvest holds about 14,000 resort-days with a lift count and 24,600 with an open/closed status, over 656 resorts. That is a median of eighteen labelled days per resort, heavily weighted to the winters the crawlers happened to visit, and the paper says so in those words: it makes an early result possible; the first winter of continuous logging is what makes the model good.
How the forecast is made
The model learns the mapping from weather that happened to what the lifts did, in the perfect-prognosis tradition. That one choice lets the same model serve three horizons: fed forecast weather inside ten days; fed climatology pulled toward the last known state at two to six weeks; and run over fifteen past winters of reanalysis weather to manufacture the long-range prior a booking three months out needs. Until the learned model passes its gate, a transparent weather heuristic stands in: the season calendar, the snow on the ground, ridge-top gusts, thaw and storm days, each factor documented and each row saying which generation produced it.
The season calendar deserves a sentence of its own, because it bit us on day one. A published window that has already closed is last season, whatever year its dates carry. Before that rule, a 200-metre hill near Trondheim merged last winter's dates with next winter's and was 75 % likely to run its lifts in September, while its own operator's page said no skiable terrain. The rule now serves the forecast, the site and this paper alike, and the failure is recorded as its motivation.
What we promised before the season
The protocol is frozen: the targets, the baselines (climatology, persistence, the bare calendar), the horizon buckets, the Brier and reliability scores, and the gate under which a learned forecast may replace the calendar on a live product, fourteen consecutive days of beating climatology and persistence in a forward-chaining backtest. Results are reported at three checkpoints, 15 January, 15 February and after 30 April 2027. The paper marks every open item, and it says so on its first page.

The first result, before the season
On 12 September the reanalysis pull finished and we ran the evaluation the paper had committed to a week earlier: hold out one winter at a time, train on the other fourteen, and ask whether the weather of a day explains what the lifts did. The test covered 24,479 archive-labelled resort-days over 655 resorts, 2011/12 to 2025/26. Against the simplest yardstick, it does. Whether any lift ran is predicted with a Brier score of 0.097 (the base rate scores 0.18 to 0.33, depending on the winter) and whether most lifts ran with 0.136; the share of lifts running is off by 0.20 on average where guessing the mean is off by 0.40. Thirteen of the fifteen winters improve on their base rate by at least 40 %.
The two that do not are 2019/20 and 2020/21, and they are the same exception. In 2020/21 the archive's Austrian resort-days ran most of their lifts on 18 % of days (70 % two winters earlier), Germany on 1 %, France and Italy on none, while Switzerland, which kept its lifts turning, sat at its usual 65 %. Lifts were closed by decree, and a model that had learned from fourteen other winters that snow and cold open lifts predicted them open. We report those winters as they are rather than exclude them: a guarantee priced on weather alone would have paid out in 2020/21 for reasons no weather feature carries, and that is worth knowing before the season, not after.
This is an alpha result, and the paper calls it that. It says the archive's sparse labels carry enough signal to learn from, and it gives the long-range tier its first real model: the same trees run over fifteen winters of reanalysis now give every resort a per-week probability that inherits what they learned about elevation, latitude, calendar and snow. It says nothing yet about forecast skill at any lead; that is the paper's claim, and it waits for the winter.
The second pass: what the weather really adds
On 3 October we asked the questions a careful reader asks next, on the same 24,479 archived days.
First, how much of that result was the season calendar? Most of it. A model that knows only the resort and its calendar already scores 0.099 for any lift and 0.140 for most lifts; adding the weather takes it to 0.096 and 0.136. Overall the weather adds 2 to 3 %. On the days a trip is actually at risk it adds more: 10 % in the first three weeks after opening, 8 to 12 % on days of rain on warm snow, 6 to 7 % on windy days. The archives mostly captured pages in mid-season, when the lifts run anyway, so the winter's daily scoring remains the real test.
Second, does the model travel? We held out one country at a time. In every country tested, the model that had never seen it still beat the season calendar there at predicting whether the lifts would run. Since 3 October the long-range curve on every resort page comes from the model, not only in the sixteen countries the archives document best.
Third, the pandemic winters. Taken out of training, they stop dragging every other winter down: on normal winters the error falls by 6 to 14 %, and the probabilities come out calibrated without any correction. The site now uses that model.
We also found a mistake of our own. The site treated 270 resorts as glaciers because a forecast band at the top of their lifts carried that name; 218 of them top out below 2,900 m, Bansko and Serre Chevalier among them. A glacier is now a height or an early season. Fixing it exposed what the false label had been hiding: big resorts keep their lifts running on machine-made snow while the weather model sees a thin base, and the ten-day outlook now allows for that.
The third pass: a third archive, and a choice per country
On 8 October we added a third source: OnTheSnow's resort pages, as web archives kept them. It more than doubled the corpus, to 52,340 resort-days at 1,125 resorts, and filled the recent winters the first two archives barely had.
More labels of the same kind help, but modestly. On the same held-out days, the retrained model lowers the error on whether any lift runs by 4 to 6 % and leaves the share of lifts running where it was. The calendar still does most of the work; the weather adds 1 to 4 %.
The gain also differs by country. The error on the share of lifts running falls by 20 % in France, 15 % in Norway, 13 % in Italy and 11 to 12 % in Spain, Sweden and the United Kingdom. It rises by 3 to 10 % in Austria, Switzerland and Bulgaria, where the archives often count lifts differently: one counts the resort, another the whole linked area. So the site now chooses per country, by a stated rule: the new model everywhere, except where it is clearly worse than the one it replaces on days neither was trained on. Austria, Switzerland and Bulgaria keep the previous model for now, and the rule runs again at every retraining.
Two checks earned their keep. In the first retraining Zermatt's February dropped from 0.86 to 0.59, because the new source counted the whole Matterhorn Ski Paradise as Zermatt's total; those counts are now left out, as another source's were in September. And the lockdown winter has to stay out of every comparison: the closures of 2020/21 made the model that expects an open February look worse in central Europe when it was not.
What the archives cannot give is each past winter's actual opening and closing dates, and how much of a resort runs on machine-made snow. Those, and this winter's daily reports, are where the next improvement should come from.
Passes four to six: what moved the model, and what did not
Between 10 and 16 October we tested five more ideas on the same held-out days. Two of them improved the forecast; the others showed where its limits are.
More pages of the same kind no longer help. A fourth pass added the rest of the OnTheSnow archive, and no country moved by more than 1 %.
Each winter's own season dates do help. The archived pages publish the opening and closing dates for about 6,800 past resort-winters, which training had replaced with this winter's dates moved back a year at a time. Read as a page had published them by the day a forecast is made, they lower the error on whether any lift runs by 2.4 %. A first run showed 12 %, but almost all of that was a leak: a 30-day forecast had read an opening that was announced later. We report the smaller number.
The operators' own lift-by-lift pages are archived too: Skiplan and Lumiplan bulletins and intermaps maps, the newest with a reason for every closure. Most captures were made at night, though, when a page shows the next day's plan, and only 1,149 days became usable. Where they overlap another source they agree on 97 % of days. That is too few to move the model.
December, when machine-made snow opens resorts, is where much of the error sits. Counting the nights cold enough for snow guns since 1 November improves December by 1.5 % and costs as much in March, so over the season it changes nothing. Finer snow data, Austria's 1 km SNOWGRID against the 31 km reanalysis, improves the forecast of most lifts running by 1.5 % and leaves the other two measures where they were. The weather's modest part is not mainly a question of resolution.
The clearest gain came from giving a country its own model, where it has enough data. Against the model that served it, Switzerland's own model lowers the error on the share of lifts running by 5.6 % and on whether any lift runs by 5.8 %; Austria's lowers the error on whether any lift runs by 9.7 %, with the other two measures about level. For most countries one shared model stays better, because the opening and closing weeks are learned from all of them together.
Since 16 October the site therefore serves Switzerland and Austria from their own models, France and Germany from the sixth pass's shared model (4 to 5 % better on whether any lift runs), Bulgaria from the model of 3 October, and every other country as before. The rule behind these choices, and the one judgment call in them, Austria, are written into the paper.
Why it matters commercially
Tour operators and resorts sell guarantees of the form refund if fewer than a given share of the lifts run on so many of your days. Pricing such a guarantee for a specific resort and week is exactly the quantity the paper forecasts, and the public API already returns the payout probability for any window, with the independence assumption stated rather than hidden.
The draft
The working paper is by Marcel Butucea, Sinorom Research, in collaboration with Skinow.eu. It is a draft: the methods and the protocol are final, six pre-season passes over the archive labels are in, and the season results are placeholders until the winter delivers them.
Sources and rights for everything the paper and the outlook rest on, from the weather models to the archive captures, are listed on our data attribution page. Publication of the labelled dataset itself waits on per-source rights; the labels derived from open sources will be released with a DOI.